Wastewater Project Update & Detours

Orchard Road Detour to start in January, 2024
Orchard Road detour

Please be advised of the detour for Orchard Road and Quinaquisset Avenue set to begin on January 8, 2024. See picture attached.

COLLECTION SYSTEM IMPROVEMENTS TOWN OF MASHPEE, MASSACHUSETTS - TWO WEEK CONSTRUCTION SCHEDULE

Falmouth Road Pump Station Route 28 Falmouth Road Building Work: Siding, Electrical Panel Boards, Painting Friday 12/22/23 ‐ Friday 1/5/24 

Mashpee Neck Road Pump Station Mashpee Neck Road Building Work: Siding, Electrical Panel Boards, Painting Friday 12/22/23 ‐ Friday 1/5/24 

Quinaquisset Ave Clipper St 40 Quinaquisset Ave Excavation and Installation of 8" Gravity Sewer and Manholes and Water Main Friday 12/22/23 ‐ Friday 1/5/24 

Orchard Road Quinaquisset Ave Falmouth Road Excavation and Installation of 8" Gravity Sewer and Manholes Monday 1/8/24 ‐ Monday 2/5/24

No work on Monday December 25th or Monday January 1st

Detour Orchard Road Jan 2024